HD HPT T2 Project
SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction. SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction. SYSCON understands what it takes to see a major construction project to completion. One of the most vital aspects of any successful project is expert planning and preconstruction.
Project Scope Details
DESIGN
MAP GROUP, INC.
GENERAL CONTRACTOR
SYSCON, LLC
MAIN SUBCONRTRACTOR
LOT AREA
4,353,386 SF
CONSTRUCTION AREA

181,134 SF

FlOORS OR ELEVATION

Main Plant: 107 FT, 3 stories

BUILDING STRUCTURES

Steel Structures

TPO Roofing

Wall Panel

MAJOR ACTIVITIES

Civil · Concrete: 19,320 CYD

Steel structures: 4,500 TONS

Siding + Roofing + Finish + M/E/P + Fire Protection

Project Scope Details
DESIGN
MAP GROUP, INC.
GENERAL CONTRACTOR
SYSCON, LLC
MAIN SUBCONTRACTOR
LOT AREA
4,353,386 SF
CONSTRUCTION AREA

181,134 SF

Project Scope Details
LOT AREA
This is some text inside of a div block.
CONSTRUCTION AREA
This is some text inside of a div block.
ELEVATION
This is some text inside of a div block.
BUILDING STRUCTURES
This is some text inside of a div block.
MAJOR ACTIVITES
This is some text inside of a div block.
DESIGN
This is some text inside of a div block.
FlOORS OR ELEVATION

Main Plant: 107 FT, 3 stories

BUILDING STRUCTURES

Steel Structures

TPO Roofing

Wall Panel

MAJOR ACTIVITES

Civil · Concrete: 19,320 CYD

Steel structures: 4,500 TONS

Siding + Roofing + Finish + M/E/P + Fire Protection